English (United Kingdom)Polish (Poland)

Sanatorium Uzdrowiskowe ZNP w Nałęczowie

Construction works progress

30 December 2015

Thermal insulation of walls

On 23 December the final acceptance of works related to thermal modernisation of the building was carried out.

Modernisation of the heating system

Waiting for connection of the cogeneration module.

 
Construction works progress

12 November 2015

Thermal insulation of walls

Carrying out thermal insulation of all walls, foundations, roofs and flat roofs, completion of roof works, rain gutters, concrete sett paving trim round the building, execution of the new lighting protection system.

Modernisation of the heating system

Execution of all new vertical heating pipework, all heaters as provided by the project were installed (351 pcs), installation works in the boiler house were completed, one gas heating boiler was removed, leakage test of the new heating system was performed, following the positive test result it was commissioned for the winter season.

 
Press releases about the investment

On 23rd , 26 th , 27 th and 30th November 2015 in the local press "Kurier Lubelski", "Gazeta Wyborcza" and "Dziennik Wschodni" was published the information about the main objectives of the investment: “Complex thermal efficiency improvement and the application of the installation is a guarantee of the high- performance production of the electricity and the heat in the building of Sanatorium Uzdrowiskowe ZNP w Nałęczowie [health resort of Polish Teacher’s Union] in Nałęczów within the Operational Programme PL04 “Saving energy and promoting renewable energy source”.

 
Construction works progress

24 September 2015

Thermal insulation of walls

In connection with closing for guests the  Sanatorium building on 23 September, thermal insulation works can be moved to the southern façade where there are hotel rooms. Therefore,  the works on balconies and terrace will start and they will be connected with the replacement of flashing, tiles, lighting protection system and thermal insulation of walls, plinths and foundations.

Modernisation of the heating system

All old heaters – 283 pcs in total – were already removed; moreover all horizontal and vertical pipework was removed in the basement as well as the pipework in the residential facilities and treatment facilities. In progress are the works related to the assembly of new heaters and vertical and horizontal pipework of the central heating system in the rooms and bathrooms.

 
Construction works progress

4 August 2015

Thermal insulation of walls           

Thermal insulation works on the northern façade of the building are in progress. Due to favourable atmospheric conditions, the contractor is slightly ahead of the schedule. Currently executed works include demolition works on the façade, earthworks at the foundations, damp insulation, thermal insulation with expanded polystyrene and mineral wool of cellar walls, plinths and building walls; the new lighting protection system is being executed as well as rain gutters and drain pipework; total thermal insulation of the flat roof with granulate material was carried out, new flashing is installed, roofs are covered with tar board.

Modernisation of the heating system

In progress are the works inside the building related to the new central heating installation. In the boiler house dismantling works are carried out; a cogeneration module was introduced to the building as well as heating water buffer tanks, the exhaust discharge system was installed on the façade of the building. 

 
Tender procedure – modernisation of the heating system

15 June 2015

On 10 June 2015 a contract was signed for the execution of construction works “Execution of modernisation works of the heating system in the building of Sanatorium Uzdrowiskowe ZNP in Nałęczów”. The tender procedure was announced on 28 April 2015. In response to the request for bid, the quotations were submitted by 10 contractors. On 26 May 2015 the information was published on the choice of the most favourable quotation which was submitted by the company “SGW Budownictwo Waldemar Stelmach”, ul. Mokra 2, 26-600 Radom. The quotation complied with all requirements and conditions as determined in SIWZ and the proposed price was the lowest out of the non-rejectable quotations. The choice criterion of the quotation was in 100% the gross price.

 
Tender procedure – thermal insulation of walls

10 June 2015

On 3 June 2015  a contract was signed for the execution of construction works “Execution of wall and roof thermal insulation in the building of Sanatorium Uzdrowiskowe ZNP in Nałęczów”. The tender procedure was announced on 23 April 2015. In response to the request for bid, the quotations were submitted by 3 contractors. On 21 May 2015 the information was published on the choice of the most favourable quotation which was submitted by the company “Przedsiębiorstwo Handlowo Produkcyjno Usługowe – Franciszek Wach”, Plac partyzantów 1, 26-713 Kazanów. The quotation complied with all requirements and conditions as determined in SIWZ and the proposed price was the lowest out of the non-rejectable quotations. The choice criterion of the quotation was in 100% the gross price.

 
Press releases about the beginning of the investment

19 february 2015

On 18th and 19th February 2015 in the local press "Kurier Lubelski" and "Gazeta Wyborcza" was published the information about the beginning and the main objectives of the investment: “Complex thermal efficiency improvement and the application of the installation is a guarantee of the high- performance production of the electricity and the heat in the building of Sanatorium Uzdrowiskowe ZNP w Nałęczowie [health resort of Polish Teacher’s Union] in Nałęczów within the Operational Programme PL04 “Saving energy and promoting renewable energy source”.

 

 
Installation of the information board

02 february 2015

On 2nd February 2015 on the facade of the building of the Health Resort of Polish Teacher’s Union in Nałęczów the information board was installed with the description of the investment: “Complex thermal efficiency improvement and the application of the installation is a guarantee of the high- performance production of the electricity and the heat in the building of Sanatorium Uzdrowiskowe ZNP w Nałęczowie [health resort of Polish Teacher’s Union] in Nałęczów” within the Operational Programme PL04 “Saving energy and promoting renewable energy source”.

 
Election of the Construction Site Inspector

26 january 2015

The Client, the Teacher’s Polish Union and the Health Resort of Teacher’s Polish Union indicate that on 26th January 2015 during the tendering process for the Construction Site Inspector (the request for quotation no. 2/PL04/2014 on 9th January 2015) the offer from the company Przedsiębiorstwo Usługowo - Projektowo - Handlowe  "AMM INSTALACJE" Adam Kukiełka headquartered in Puławy was selected.