Construction works progress

12 November 2015

Thermal insulation of walls

Carrying out thermal insulation of all walls, foundations, roofs and flat roofs, completion of roof works, rain gutters, concrete sett paving trim round the building, execution of the new lighting protection system.

Modernisation of the heating system

Execution of all new vertical heating pipework, all heaters as provided by the project were installed (351 pcs), installation works in the boiler house were completed, one gas heating boiler was removed, leakage test of the new heating system was performed, following the positive test result it was commissioned for the winter season.