English (United Kingdom)Polish (Poland)

Sanatorium Uzdrowiskowe ZNP w Nałęczowie

Construction works progress

24 September 2015

Thermal insulation of walls

In connection with closing for guests the  Sanatorium building on 23 September, thermal insulation works can be moved to the southern façade where there are hotel rooms. Therefore,  the works on balconies and terrace will start and they will be connected with the replacement of flashing, tiles, lighting protection system and thermal insulation of walls, plinths and foundations.

Modernisation of the heating system

All old heaters – 283 pcs in total – were already removed; moreover all horizontal and vertical pipework was removed in the basement as well as the pipework in the residential facilities and treatment facilities. In progress are the works related to the assembly of new heaters and vertical and horizontal pipework of the central heating system in the rooms and bathrooms.